The Rajiv Gandhi Seva Kendra of Buromunda panchayat under Gaisilat block in Bargarh district was handed over in 2012 February. When the building was handed over, it was partially completed. Only the rooms and building portion was complete. Two rooms with a veranda and a toilet was complete. Fans and electrification wearing is complete. Exterior Colour paint is complete but still so many things were not complete while the building was inaugurated and opened for public.
It is been 5 years now and one term of the elected Sarpanch, Samiti members, and Chairman etc are going to end. But according to the project proposal the Rajiv Bhawan is incomplete with toilet, over-head water-tank, Air conditioner (AC), Boundary wall, electric connection, etc.
As per the sources approximately 7 lakh 90 thousands have been used out of the total allotted budget.